Skip to content
609-264-248
bodex.bhp@wp.pl
Homepage
About the company
Offer
EHS and Fire Protection Services
Health and safety
Fire Protection
Training and courses
Health and safety
First aid
Forklifts
Learning
Test
Mobile platforms
Learning
Test
Overhead cranes
Learning
Test
Hoists and winches
Hookmen and signalmen
Warehouseman
Contact
Homepage
About the company
Offer
EHS and Fire Protection Services
Health and safety
Fire Protection
Training and courses
Health and safety
First aid
Forklifts
Learning
Test
Mobile platforms
Learning
Test
Overhead cranes
Learning
Test
Hoists and winches
Hookmen and signalmen
Warehouseman
Contact
Test: general purpose cranes, hoists and winches
single-choice test
11 of 15 correct answers pass the exam
duration of the exam 30 minutes
"Finish test" button shows the result of the test
ROZPOCZNIJ TEST
WYNIK
NOWY TEST
NOWY TEST
#1.
Based on the drawing shown, indicate the correct way to attach the hook:
a ) A
b ) B
c ) C
d ) D
#2.
The following figure shows:
a ) specialized slings for transporting steel and concrete pipes
b ) a tick gripper for handling scrap metal
c ) specialized slings for transporting loads placed on transport pallets
d ) element of rail tongs
#3.
The safety element installed in the lifting mechanism of cranes can be:
a ) capacity limiter
b ) limit switch of the lifting mechanism
c ) friction overload clutch
d ) all answers are correct
#4.
How should large-sized cargoes be prevented from fluctuating?
a ) the hookman holds the load with his hand
b ) the operator holds the load with his hand
c ) using a belaying rope attached to the load
d ) all of the above answers are correct
#5.
Unless otherwise provided by the manufacturer, the limit switch of the lifting mechanism in the “down” direction should be set so that:
a ) there is at least 1.5 m of rope left on the drum
b ) there is at least 2.5 m of rope left on the drum together with the section used to secure it
c ) there is at least 1.5 reels of rope left on the drum, not counting the section used to secure it
d ) at least half the length of the rope is left on the drum
#6.
The weight of a cargo consisting of 40 packages of 25 kg each is:
a ) 800 kg
b ) 1000 kg
c ) 1100 kg
d ) 900 kg
#7.
Which of the following defects disqualifies a cable sling from further operation?
a ) the strand breaks in the rope
b ) local reduction in diameter due to breakage of the rope core
c ) basket-shaped deformation
d ) all answers are correct
#8.
If the operator notices spontaneous slow lowering of the load with an overhead crane during load transfer, then:
a ) this means a failure of the lifting mechanism brake
b ) this means a temporary reduction in supply voltage, which will pass spontaneously
c ) this is the effect of tripping the load limiter
d ) in signalman controls, this is a perfectly normal situation
#9.
If there is limited visibility of the cargo storage area, you should:
a ) refuse to do the work
b ) enlist the help of a hook (signalman)
c ) first try to put down without the help of the hookman, only when it fails to ask him for help
d ) estimate the transport route, and then put down the cargo yourself
#10.
In the case of operation of two or more cranes on a single track, electrical protection to prevent the cranes from invading each other is:
a ) limit switches
b ) anti-collision system
c ) load limiters
d ) movement release stops
#11.
The agreed repair or upgrade of technical equipment can be performed:
a ) repairer or retrofitter who holds an authorization issued by the authority of the relevant technical supervision unit
b ) operating a technical device with relevant experience in repairs or upgrades
c ) a maintenance technician with relevant experience in repairs or upgrades
d ) to a small extent competent operator
#12.
A change in technical parameters or a change in the design of a technical device is treated as:
a ) modernization of the technical device
b ) repair of a technical device
c ) repairing defects and other irregularities of the technical device
d ) manufacture of new equipment
#13.
What is wind protection used for?
a ) protect against the effects of lightning strikes on the crane structure
b ) protect against unintentional movement of the crane
c ) to the intended braking of the crane driving mechanism during operation
d ) to immobilize the bridge structure in order to safely perform crane work during high winds
#14.
An operator of a technical device may undertake work when:
a ) the device has a valid decision authorizing its operation, if required by the relevant regulations
b ) has a qualification certificate of the appropriate category
c ) the device has a current positive maintenance inspection result
d ) all of the above conditions must be met simultaneously
#15.
Repair and modernization of a technical device is performed:
a ) operator within the scope of his skills
b ) conservator
c ) authorized establishment
d ) operating
Previous
Zakończ test